SLOUGH MULTIFUEL

15,000mÂł soil removed to prepare enabling works for Slough Multi-fuel

SERVICES
Groundworks

TIMESCALE
August 2020 – May 2021

CLIENT
Scottish and Southern Energy

WHERE
Slough, West London

CATEGORY
Energy

The team worked extended hours to successfully achieve the tight timescales. This allowed the main build for the power station to start on time. The project was achieved with zero incidents.


Risks

Numerous unrecorded buried live assets. Working around live HV cables and gas pipes. Strict timescales with substantial financial impact for delays.

Value engineering

The main gas line traversing the site was safely diverted around the perimeter. This involved constructing 50 RC concrete foundations with precisely installed holding down bolts to secure the steel frame.

To manage the logistics, the team put together a detailed plan — safely removing over 4,000 lorry loads of material from site and importing over 2,000.

Works included

  • Principal Contractor duties

  • Removal of redundant pipes and cables

  • Breaking and removing 5,000m3 of concrete

  • Ground remediation

  • 15,000m3 of unsuitable soil removed

  • 7m deep cofferdam

  • 250m long RC culvert

  • Service diversion